90M ROADWAY FALL 5 TRIPPER DRIVE INSTALLATION
METROPOLITAN
Recovery of roadway fall and additional excavation to facilitate installation of the inline tripper drive. Additional cut-outs for the drive modules had to be shot fired and supported and sections of the roadway “straightened” to allow for installation of a trunk conveyor.